Rancangan Tampak Depan & Samping Musholla

    TAMPAK DEPAN


TAMPAK SAMPING

Baca Selengkapnya..

Laporan Keuangan Per 26.01.2011

1.PEMASUKAN & PENGELUARAN DANA SD TGL 26 JANUARI 2011
JUMLAH
 TOTAL PENERIMAAN SUMBANGAN DARI WARGA (DI REK BSM & BCA)
  177,264,700
PENERIMAAN SUMBANGAN DI REK BSM    
    88,233,293
PENERIMAAN SUMBANGAN DI REK BCA    
    89,031,407
 PENGELUARAN UNTUK PEMBANGUNAN MUSHOLA  SD TGL 26 JAN 2011
    84,473,444
 TOTAL SALDO (DI REK BCA & BSM + CASH ON HAND)
    92,791,256
SALDO DI REKENING BSM PER 26 JAN 2011
    33,832,849
SALDO DI REKENING BCA PER 26 JAN 2011
    56,721,407
SALDO CASH ON HAND
       2,237,000
ACUAN DASAR
TOTAL PENERIMAAN- TOTAL PENGELUARAN = SALDO BCA+ SALDO BSM + CASH ON HAND 
2.RINGKASAN PENGELUARAN DANA SD TGL 26 JANUARI 2011

NO
PENGELUARAN
JUMLAH
1
 PERINCIAN PENGELUARAN
       1,275,000
2
 PERINCIAN PENGELUARAN
       1,105,000
3
 PEMBELIAN MATERIAL DAN DP DI TK SUMBER JOYO
    71,071,000
4
 ACARA PELETAKAN BATU PERTAMA, BIAYA BANK
       2,562,000
5
 BIAYA TUKANG (ONGKOS KERJA TUKANG)
       8,265,000
6
 BIAYA LAIN LAIN
          195,444
    84,473,444
3.SUMBANGAN MATERIAL YG TELAH DITERIMA PER 26 JAN 2011
1
 PASIR                        ( Truk )
                       3
2
 BATU CORAL             ( Truk )
                       3
3
 BATU BATA               ( Biji )
               5,000
4
 SEMEN                      ( Zak )
                  105
4.KEBUTUHAN  DANA  PEMBANGUNAN  MUSHOLA 
  489,353,000
5.PEMASUKAN SD TGL 26 JANUARI 2011 
  177,264,700
6.KEKURANGAN DANA SAMPAI DENGAN TGL 26 JANUARI 2011 
312,088,300

Baca Selengkapnya..

RENCANA BIAYA PEMBANGUNAN MUSHOLLA

No
Item Pekerjaan
Vol
Sat
Harga Sat
Jumlah Harga
I
PEKERJAAN PERSIAPAN




1
Uitzet & Bouplank
120.000
M1
9.000
1.080.000,00
2
Bonglar paving existing
181.250
M2
5.000
906.250,00
3
Pembuatan Direksi keet & gudang
1.000
unit
2.000.000
2.000.000,00


Sub Total Pek. Persiapan
3.986.250,00






II
PEKERJAAN TANAH




1
Galian Tanah pondasi menerus
71.604
M3
25.000
1.790.100,00
2
Galian tanah pondasi strauss Ø 30 cm
140.000
M3
25.000
3.500.000,00
3
Urug kembali lubang pondasi
53.703
M3
10.000
537.030,00
4
Urugan sirtu u/ peninggian elevasi
42.090
M3
60.000
2.525.400,00
5
Pemadatan urugan sirtu
150.460
M2
6.000
902.760,00


Sub Total Pekerjaan Tanah
9.255.290,00






III
PEKERJAAN PONDASI BETON




1
Lantai kerja 3 cm
89.505
M2
19.300
1.727.446,50
2
Cor Pondasi strauss Ø 30 cm, P=4m
9.608
M3
1.636.000
15.719.342,40
3
Cor pondasi Menerus 85x200x20 m
22.113
M3
2.515.000
55.614.195,00
4
Rabat lantai 7 cm ( camp 1:3:5 )
9.905
M3
630.000
6.240.150,00


Sub Tot.Pek. Pondasi beton
79.301.133,90






IV
PEKERJAAN BETON STRUKTUR ATAS




1
Cor kolom praktis 15/15 cm
2.590
M3
3.120.000
8.080.800,00
2
Cor kolom 15x46 cm
1.760
M3
3.327.000
5.855.520,00
3
Cor kolom 15x55 cm
5.270
M3
2.881.000
15.182.870,00
4
Cor kolom 20x20 cm
0.320
M3
3.439.000
1.100.480,00
5
Cor kolom 20x46 cm
4.563
M3
3.327.000
15.181.766,40
6
Cor kolom 20x55 cm
1.364
M3
2.915.000
3.976.060,00
7
Cor kolom 20x72,5 cm
1.798
M3
2.786.000
5.009.228,00
8
Cor balok ring 15/15 cm
3.040
M3
3.120.000
9.484.800,00
9
Cor balok 15x30 cm
3.839
M3
3.516.000
13.497.924,00
10
Cor balok 20x50 cm
3.200
M3
3.135.000
10.032.000,00
11
Cor dak beton T=12cm, K 225
10.448
M3
2.738.000
28.606.624,00


Sub tot.Pek. Beton Struktur
116.008.072,40






V
PEKERJAAN PASANGAN DINDING




1
Pekerjaan dinding bata
255.601
M2
66.500
16.997.466,50
2
Plesteran & acian dinding bata
562.322
M2
29.000
16.307.343,80


Sub total Pek. Pasangan
33.304.810,30



VI
PEKERJAAN ATAP




1
Pasang kuda-kuda baja WF 200x100
740.920
Kg
15.000
11.113.800,00
2
Pasang baut angkur Ø 16mm,50-10 cm
32.000
Unit
50.000
1.600.000,00
3
Pasang rangka atap galvalume
69.000
M2
150.000
10.350.000,00
4
Pasang penutup atap genteng beto flat @7000/pcs
69.000
M2
97.500
6.727.500,00
5
Pasang Bubungan
28.000
M1
100.000
2.800.000,00
6
Pasang listplank papan kayu nyatoh 3/25
30.000
M1
85.000
2.550.000,00
7
Pasang plapond gypsum (rangka hollow galvalume T=0,5mm)
137.000
M2
80.000
10.960.000,00
8
Pasang list gypsum H=12cm
169.500
M1
17.500
2.966.250,00


Sub Total Pek. Atap
49.067.550,00






VII
PEKERJAAN LANTAI




1
Pasang keramik granito 60x60 @ 250rb/doz
121.000
M2
300.000
36.300.000,00
2
Pasang keramik granite 40x40 trap tangga teras @ 200rb/doz
11.500
M2
250.000
2.875.000,00
3
Pasang keramik lantai 20x20 area wudlu @ 85rb/doz
9.000
M2
135.000
1.215.000
4
Pasang keramik dinding area wudlu @ 125rb/doz
30.000
M2
175.000
5.250.000


Sub total pekerjaan lantai
45.640.000,00






VII
PEKERJAAN PENGECATAN




1
Cat dinding luar ex dulux weather shield (warna muda)
562.322
M2
18.500
10.402.960,70
2
Cat plapond ex dulux (warna muda)
137.000
M2
20.000
2.740.000.00
3
Pengecatan duco (warna emas) ornament besi hollow 1
4.000
Unit
300.000
1.200.000.00
4
Pengecatan duco (warna emas) ornament besi hollow 2
4.000
Unit
200.000
800.000.00
5
Pengecatan duco (warna emas) ornament besi hollow 3
16.000
Unit
100.000
1.600.000.00
6
Pengecatan duco (warna hijau) ornament besi hollow 4
6.000
Unit
200.000
1.200.000.00
7
Pengecatan duco (warna hijau) ornament besi hollow 5
2.000
Unit
200.000
400.000.00
8
Pengecatan duco (warna emas) pintu R.Wudlu
2.000
Unit
200.000
400.000.00
9
Sanding Pintu+kusen (R.imam&R.sound)
4.000
Unit
550.000
2.000.000.00


Sub total Pek. pengecatan
20.742.960.70






IX
PEKERJAAN CURTAIN WALL &PINTU KACA




1
Pekerjaan curtain wall kaca tempered 8mm
79.200
M2
600.000
47.520.000,00
2
Pekerjaan pintu (double) kaca tempered
3.000
Unit
6.000.000
18.000.000,00
3
Pekerjaan kaca artistic (stained kuningan) u/ tempat imam
0.650
M2
1.800.000
1.170.000,00
4
Pekerjaan kaca artistic (Kaca grafir Full Colour & Full Block ) u/ pintu taekwood
0.320
M2
550.000
176.000,00


Sub Tot Pekerjaan Kaca
66.866.000,00
X
PEKERJAAN PINTU KAYU




1
Kusen pintu kayu nyatoh
28.800
M2
85.000
2.448.000.00
2
Daun Pintu double teakwood + accesoris
4.000
Unit
750.000
3.000.000.00


Sub tot Pek. Pintu Kayu
5.448.000.00






XI
PEKERJAAN INSTALASI LISTRIK




1
Instalasi Titik Lampu
17.000
Ttk
100.000
1.700.000
2
Instalasi stop kontak
10.000
Ttk
100.000
1.000.000
3
Pasang lampu down light (include SL 32 W )
15.000
Ttk
150.000
2.250.000
4
Pasang lampu SL 32 W + armature
2.000
Ttk
50.000
100.000
5
Pasang instalasi u/ sound system
4.000
Unit
50.000
200.000
6
Pemasangan lampu gantung di area utama
1.000
Unit
5.000.000
5.000.000
7
Pemasangan lampu gantung di kubah sudut
4.000
Unit
1.500.000
6.000.000


Sub Tot Pekerjaan Listrik
16.250.000.00






XII
PEKERJAAN INSTALASI AIR




1
Instalasi air bersih ( PVC AW ¾” )
30.000
M1
15.000
450.000,00
2
Instalasi air kotor ( PVC AW 3” )
15.000
M1
45.000
675.000,00
3
Pasang kran air wudlu ex TOTO
10.000
Unit
200.000
2.000.000,00
4
Pasang avoor lantai R. wudhu
4.000
Unit
75.000
300.000,00
5
Pasang pompa air
1.000
Unit
1.000.000
1.000.000,00
6
Pembuatan tendon air (tanam) kapasitas 2 m3
1.000
Unit
2.000.000
2.000.000,00


Sub Tot Pek Instalasi Air
6.425.000,00






XIII
PEKERJAAN ORNAMEN




`1
Ornamen 1
4.000
Unit
1.308.000
5.232.000,00
2
Ornamen 2
4.000
Unit
810.000
3.240.000,00
3
Ornamen 3
16.000
Unit
300.000
4.800.000,00
4
Ornamen 4
6.000
Unit
700.000
4.200.000,00
5
Ornamen 5
2.000
Unit
700.000
1.400.000,00
6
Pintu R. Wudlu
2.000
Unit
555.000
1.110.000,00
7
Kanopy Type A (penutup kaca tampered 8 mm)
2.000
Unit
5.652.000
11.304.000,00
8
Kanopy Type B (penutup kaca tampered 8 mm)
2.000
Unit
1.386.000
2.772.000,00


Sub Tot Pek. Ornament
34.058.000,00






XIV
PEKERJAAN LAIN-LAIN




1
Pemasangan kubah di atap induk
1.000
Unit
1.500.000
1.500.000,00
2
Pasang AC

Unit


3
Pasang Kipas Angin

Unit


4
Pembersihan area
1.000
ls
1.500.000
1.500.000,00


Sub tot pek lain-lain
3.000.000,00






i
TOTAL PERKIRAAN BIAYA PEMBANGUNGAN MUSHOLLA
489.353.067.30






ii
P E M B U L A T A N
489.353.000,00